Fibrwrap Construction Lebanon SARL

Fibrwrap Lebanon: Pre-stressed Concrete Pipe Repair of PPL Montana, Montana, USA

Market Sector: Industrial, Silos and Energy Producing Facilities, Pipelines and Liquid Storage Structures

Technology: Fyfe Europe

Country: USA

Pre-stressed Concrete Pipe Repair of PPL Montana, Montana, USA

Project: Pre-stressed Concrete Cylinder Pipe Repair of PPL Montana
Location: Montana, USA
Client: PPL Montana LLC
 

Scope of Works:
• Repair of more than 20 sections of PCCP

 

Project Description:
Over 100 lineal feet of six 72 inch diameter PCCP sections in PPL Montana Colstrip Power Plant Unit suffered cracks both in the longitudinal and the circumferential directions due to accidental transient pressure. The design working pressure of the pipelines is 65 psi and the soil cover height is 8 ft.
Fibrwrap® Construction installed the Fyfe Company uni-directional Tyfo® SCH-41 System both in the circumferential and longitudinal directions as determined by Simpson Gumpertz & Heger Consulting Engineers to restore the pipe sections to their original capacity and to account for future transient pressure.
Implementing new age technology, the owner was provided an alternated to conventional construction, which resulted in vas time savings, reduced remedial costs, and reduced shut down time.

Similar Projects